|
|
Sample: Week #1 of 52 Weekly
Email Messages
Project Management Tip of
the Week: Manage Risk
This weekly email
contains project management tips to assist you in managing your project and
your team. It serves as a reminder to manage projects with discipline and
rigor - always in line with the size and complexity of the project. The
content comes from the TenStep Project Management Process®and may be
reviewed at
www.TenStep.com.
----- add your opening
organizational announcements here
Positive Risk
We typically associate project risk with a negative connotation. However,
there is a concept of opportunity risk or positive risk. In these instances,
the project manager or project team may introduce risk to try to gain much
more value later. For instance, a team may decide to utilize a new
technology on their project because they think it will result in dramatic
effort and cost savings. Of course, there is also a chance the new
technology will not work. However, the team introduces the risk because the
potential for gain. This is an example of intelligent risk taking or
positive risk. However, from a definition standpoint, the TenStep Manage
Risk process, and most project management methodologies, assumes that the
risks we are managing are negative risks. They need to be addressed so that
the underlying potential problem does not occur.
Alternatives Strategies for the
Risk Response
Once risks have been
identified, there are a number of options that the project manager might
consider for responses.
-
Leave it. In this approach, the
project manager looks at the impact the risk condition would have on the
project and decides that nothing needs to be done to mitigate the risk.
This approach should only be used for low impact risks or those that are
unlikely to occur. This approach is dangerous for high and medium risks.
-
Monitor the risk. In this case, the
project manager does not proactively mitigate the risk, but monitors it to
see whether it is more or less likely to occur as time goes on. If it
looks more likely to occur, the team must formulate a different response
at a later time. This approach can work for serious risks that are not
likely to occur. Rather than put a plan in place immediately, the project
manager creates a plan only if it looks likely that the risk will occur.
The advantage is that scarce resources are expended only on those risks
that are likely to occur. The disadvantage is that the delay in addressing
the risk might make it less likely that the risk can be successfully
mitigated in the future.
-
Avoid the risk. Avoiding the risk
means that the condition that is causing the problem is eliminated. For
instance, if a part of the project has high risk associated with it, then
the whole part of the project is eliminated. Risks associated with a
particular vendor might be avoided if another vendor is used instead. This
is a very effective way to eliminate risks but obviously can be used only
in certain unique circumstances.
-
Move the risk. In some instances, the
responsibility for managing a risk can be removed from the project by
assigning the risk to another entity or third party. For instance,
installation risks might be eliminated by outsourcing this function to a
third party. The third party might have particular expertise that allows
them to do the work without the risk. Even if the risk is still present,
it now is up to another party to resolve.
-
Mitigate the risk. In most cases, this
is the approach to take. Usually proactive steps must be taken if a risk
has been identified to ensure that the risk does not occur. Another of the
goals of mitigation is to ensure that the effect (impact) of the risk is
minimized if it does occur. For the purposes of the TenStep Project
Management Process, it is generally assumed that risk plans are
established to mitigate the risk.
-----
add your closing content here |
|